Control has added the ability to set a Due Date on the Line Item level. This page contains information explaining this new feature.

Concept

Control originally supported Order level Due Dates. For many users, this is sufficiently granular since the entire order is normally due at the same time. However, this approach has some limitations for the following types of customer:

For both of these customers, the Order level Due Date is insufficient. As an example, imagine the following scenario:

Order 1234 is for a single digital print (to keep things simple) and must be shipped to the customer location for arrival within 7 days. The price the customer is given is $100, which represents $70 for the printing and $30 for the design. The order is entered as one line item for $70 (digital print) and one line item for $30 (design). The order is being shipped (at no additional charge) via 2 day shipping.

In this case, the order due date (at the customer location) is 7 days. Clearly, starting the design or even the print 6 days from now is too late, even if it only takes an hour to print. These modifications would allow Order 1234 to be set up as follows:

Of course, the exact dates chosen in any given business might vary, but hopefully the point is still conveyed.

Cautions

No known cautions at this time

How to Use the new Due Date fields

Production Terminal Changes

In Production Terminal, the filter for the Due Date range now filters on the Line Item Due Date instead of the Order Due Date.

Report Changes

Source